Guides · 27 October 2026

What the May 2025 Bali Blackout Taught Us About Standby Power

When most of the island lost power on 2 May 2025, the hotels that coped were not the ones with the biggest generators. They were the ones that had tested what happens in the first ten minutes.

BCM Project Team · 1 min read

Standby generator set

Illustrative photo: a packaged standby generator. Photo by Cantons-de-l'Est via Wikimedia Commons, CC0.

On the afternoon of Friday 2 May 2025, power went out across most of Bali. PLN pointed to a fault on the undersea cable link between Java and Bali; the provincial government, citing PLN, said around 80 percent of the province was affected. Power was restored to the whole island by early the next morning.

 

Hotels, hospitals and the airport largely kept running on backup generators. But “we have a generator” and “the hotel kept working” are not the same statement, and the gap between them is almost always found in the first ten minutes.

 

Five things to check before the next one

1. Test under load, not just at idle

A generator that starts every Monday morning and runs unloaded for fifteen minutes proves very little. Schedule periodic tests where the set actually carries the building’s essential load, so that cooling, fuel delivery and voltage regulation are proven under real conditions.

 

2. Prove the changeover

The automatic transfer switch (ATS) is the part most likely to be forgotten. Test the full sequence — mains failure detection, generator start, transfer, and the return to mains — and time it.

Modular circuit protection devices

Illustrative photo: modular circuit protection devices. Photo by Retired electrician via Wikimedia Commons, CC0.

3. Know exactly what is on the essential board

Over years of renovation, circuits migrate. The essential board should feed life safety systems, lifts, domestic water pumps, cold rooms, IT and security — and not, for example, the spa’s steam generator someone moved onto it in 2016. Walk the schedule against reality once a year.

 

4. Remember that water is electric

Most Bali properties draw water from wells and booster pumps. If the pumps are not on standby power, the taps run dry within hours even though the lights are on. The same applies to sewage lift stations.

 

5. Plan the restart

When mains returns, chillers, large motors and every air-conditioning unit trying to start at once can trip the incoming supply. A staged restart sequence — written down and practised — protects both the equipment and the rest of the evening.

 

Fuel is the quiet risk

Know how many hours of autonomy the day tank and bulk tank actually give at the essential load, who supplies fuel at short notice, and when the stored diesel was last checked for water and sediment. An outage that runs into the night is a fuel problem, not a generator problem.